Formule de verges cubes pour dalles, semelles et colonnes

Comment Calculer les Verges Cubes de Beton

D'abord la reponse: verges cubes = (longueur x largeur x epaisseur en pieds) / 27. Une dalle de 10x10 pi a 4 pouces necessite 1.36 vc avec 10% de dechets.

Formule

vc = (L × l × E) ÷ 27

L, l en pieds. E en pieds (divisez les pouces par 12). Ajoutez 5-15% de dechets.

Dalle 10×10 pi, 4 po

1.23 vc avant dechets

Avec 10% de dechets: 1.36 vc ou environ 62 sacs de 80 lb.

Calculateur de yardage de béton

Calculer le yardage de béton

10 × 10 × (4/12) ÷ 27 × 1.10 = 1.36 yd³

Yards cubes

1.36

Pieds cubes

36.7

80 lb bags

62

Interactive workflow

Run the numbers, then save or export the project

View planning notes
Best reviewed quote
Ready-mix supplier A
Red flags
0
Proposal total
$3,824
Pour window
171 min
Couts locaux par defaut et memoire ZIP

Valeurs par defaut sauvegardees

Reuse bag price, ready-mix price, delivery fee, and waste factor across quote reviews.

Hypothèses locales
ZIP47474
1 yd3 as bags$259
1 yd3 ready-mix$475
Break-even3.3 yd3
  • 80 lb bag price: $6
  • Ready-mix price per yd3: $165
  • Delivery + short-load: $310
  • Wait-time rate: $95 per hour

Enregistrez cette estimation ou telechargez un rapport PDF

Le rapport PDF utilise le resultat calcule actuel. Enregistrez dabord lestimation lorsque vous souhaitez reutiliser les donnees plus tard.

La formule
vc = (Longueur × Largeur × Epaisseur en pieds) ÷ 27.
Facteur de dechets
5-8% pour les dalles simples, 10% pour le residentiel standard.
Sacs vs pret-a-gacher
Comparez le cout des sacs avec la livraison pret-a-gacher.

Concrete yardage checklist

Before calling a ready-mix plant with your order.

Signal to checkWhat it meansNext step
Dimensions measuredLength, width, and thickness measured at the actual site.Measure twice — being off by 1 inch on a large slab adds up fast.
Waste addedAdded 5–15% waste to the calculated volume.Use 10% for flat slabs. Add more for steps, curved edges, or uneven sub-base.
Order rounded upRounded up to the nearest 0.25 yd³.Plants typically sell in 0.25 yd³ increments. Running short mid-pour causes cold joints.
Minimum checkedConfirmed the plant's minimum load (typically 1–3 yd³).Small orders may trigger a short-load fee. Ask when you call.

Related concrete planning tools

Move from a single calculation into a purchase, proposal, or pour-day decision with connected calculators and checklists.

Comment calculer les verges cubes de beton?

Longueur (pi) × Largeur (pi) × Epaisseur (pi) ÷ 27 = vc. Convertissez l'epaisseur: 4 pouces = 0.333 pi.

Combien de verges cubes pour une dalle 10×10 pi?

A 4 pouces: (10×10×0.333)÷27 = 1.23 vc. Avec 10% de dechets: 1.36 vc.

Combien de sacs de 80 lb par verge cube?

Environ 45 sacs de 80 lb par vc.

Quel facteur de dechets utiliser?

10% pour le travail residentiel standard.

Planning disclaimer

Les calculs de volume sont uniquement a des fins de planification. Le beton reel necessaire depend des conditions du site et de la precision du coffrage.